Widening and strengthening of existing road to 2-lane with paved shoulders
From Km.0/0 to Km.12/0(Length=12.00Km) of NH-51 in Assam under SARDP-NE, Phase ‘A’.
- Ref of sanction: No.H-12014/25/AS/SARDP-NE/NH-10,dt.20.02.2007
- Sanctioned Amt.: Rs. 2093.00 Lakh
- Award Amount: Rs 18,15,79,251.00
- Ref. of Issue of Notice to Proceed with the work: No.NHR.6/2006/Pt/46,dt.28.03.2007
- Name of Contractor: M/S Sweety Real Estates Pvt. Ltd., P.P.Road, Rehabari, Guwahati-8
- Stipulated Time of completion: 24(Twenty-Four) months.
- Date of Completion: 31.03.2009
Re-construction/widening to 2-lane of NH-37 extension
From Islampur Tiniali to Shantipur Gate (Length=10.437km) in Assam, under Arunachal Pradesh package of Roads and Highway of SARDP-NE(Job No.037-Ar.Pkg-2010-11-014)
- Ref of sanction: NH-12013/10/2009/AS/Ar.Pkg/NH-9, dt.31.08.2010
- Sanctioned Amt.: Rs.2336.64 lakh
- Award Amount: Rs.20,99,02,046.00
- Ref. of Issue of Notice to Proceed with the work: No. NHC/BR/6/2009/Pt/63 ,dt.26.11.2010
- Name of Contractor: Sri J.K. Mahanta, R.G.B. Road, Usha Court, Guwahati-21
- Stipulated Time of completion: 18 (Eighteen) months
- Date of Completion: 31.03.2014
Strengthening including construction of paved shoulder
From km. 816.012 to 829.000 including improvement of connecting roads meeting NH-31 (Job No. 031-AS-2009-10-082)
- Ref of sanction: NH-12014/53/2009/AS/NH-10, dt.25.11.09
- Sanctioned Amt.: Rs.2071.00 lakh (original), Rs 2384.00 (Revised)
- Award Amount: Rs. 19,14,26,532.00
- Ref. of Issue of Notice to Proceed with the work: No. NHR 30/2009/Pt/63, dt.24.05.2010
- Name of Contractor: Shree Gautam Construction Co. Ltd. ,4th Floor, Amaze Tower, A.T.Road, Opp. Panbazar Overbridge,Guwahati-1
- Stipulated Time of completion: 24 (Twenty-four) months
- Date of Completion: 31.03.2012
Strengthening of existing 2-lane road and construction of paved shoulders
From km. 679.217 to km.687.600 (Length=8.383Km) of NH-37 (Talap –Dhola section).(Job No.SARDP-NE/NH-37/AS/PWD/2010-11-156)
- Ref of sanction: NH-12014/03/2009/AS/NH-10, dt.23.07.10
- Sanctioned Amt.: Rs.1960.42 lakh
- Award Amount; Rs. 17,13,16,416.00
- Ref. of Issue of Notice to Proceed with the work: No. NHR 28/2009/Pt/22, dt.06.09.2010
- Name of Contractor: Sri J.K. Mahanta, R.G.B. Road, Usha Court, Guwahati-21
- Stipulated Time of completion: 24 (Twenty-four) months
- Date of Completion: 19.09.2012