Some Completed Projects

Widening and strengthening of existing road to 2-lane with paved shoulders

From Km.0/0 to Km.12/0(Length=12.00Km) of NH-51 in Assam under SARDP-NE, Phase ‘A’.

  1. Ref of sanction: No.H-12014/25/AS/SARDP-NE/NH-10,dt.20.02.2007
  2. Sanctioned Amt.: Rs. 2093.00 Lakh
  3. Award Amount: Rs 18,15,79,251.00
  4. Ref. of Issue of Notice to Proceed with the work: No.NHR.6/2006/Pt/46,dt.28.03.2007
  5. Name of Contractor: M/S Sweety Real Estates Pvt. Ltd., P.P.Road, Rehabari, Guwahati-8
  6. Stipulated Time of completion: 24(Twenty-Four) months.
  7. Date of Completion: 31.03.2009

Re-construction/widening to 2-lane of NH-37 extension

From Islampur Tiniali to Shantipur Gate (Length=10.437km) in Assam, under Arunachal Pradesh package of Roads and Highway of SARDP-NE(Job No.037-Ar.Pkg-2010-11-014)

  1. Ref of sanction: NH-12013/10/2009/AS/Ar.Pkg/NH-9, dt.31.08.2010
  2. Sanctioned Amt.: Rs.2336.64 lakh
  3. Award Amount: Rs.20,99,02,046.00
  4. Ref. of Issue of Notice to Proceed with the work: No. NHC/BR/6/2009/Pt/63  ,dt.26.11.2010
  5. Name of Contractor: Sri  J.K. Mahanta, R.G.B. Road, Usha Court, Guwahati-21
  6. Stipulated Time of completion: 18 (Eighteen) months
  7. Date of Completion: 31.03.2014

Strengthening including construction of  paved shoulder

From km. 816.012 to 829.000 including improvement of connecting roads meeting NH-31 (Job No. 031-AS-2009-10-082)

  1. Ref of sanction: NH-12014/53/2009/AS/NH-10, dt.25.11.09
  2. Sanctioned Amt.: Rs.2071.00 lakh (original),  Rs 2384.00 (Revised)
  3. Award Amount: Rs. 19,14,26,532.00
  4. Ref. of Issue of Notice to Proceed with the work: No. NHR 30/2009/Pt/63, dt.24.05.2010
  5. Name of Contractor: Shree Gautam Construction  Co. Ltd. ,4th Floor, Amaze Tower, A.T.Road, Opp. Panbazar Overbridge,Guwahati-1
  6. Stipulated Time of completion: 24 (Twenty-four) months
  7. Date of Completion: 31.03.2012

Strengthening of existing 2-lane road and construction of paved shoulders

From km. 679.217 to km.687.600 (Length=8.383Km) of NH-37 (Talap –Dhola section).(Job No.SARDP-NE/NH-37/AS/PWD/2010-11-156)

  1. Ref of sanction: NH-12014/03/2009/AS/NH-10, dt.23.07.10
  2. Sanctioned Amt.: Rs.1960.42 lakh
  3. Award Amount; Rs. 17,13,16,416.00
  4. Ref. of Issue of Notice to Proceed with the work: No. NHR 28/2009/Pt/22, dt.06.09.2010
  5. Name of Contractor: Sri  J.K. Mahanta, R.G.B. Road, Usha Court, Guwahati-21
  6. Stipulated Time of completion: 24 (Twenty-four) months
  7. Date of Completion: 19.09.2012